Seneca Valley School District
Proud of the Past, Committed to the Future

September 2026

  • Massaro Corp. (General Contractor): Continued demolition at the canopy of the District Office entrance. Concreate was cut to prepare for new structural beam connections. Work also continued on the modified student walkway and overhead protection area between the Senior High School (SHS) and Intermediate High School (SHS).
    • R & S Concrete: Installed foundations and retaining walls for new SHS parking area. Foundation work continued in Area AC, including excavation, concrete walls and preparation for the new floor.
    • Century Steel: Continued installing structural steel and metal decking in Areas AA and AB.
  • Blackhawk Neff (Electrical): Installed electrical conduit for the new electrical room in the basement of the existing IHS. Work also continued on the new SHS parking area, including conduit and foundations for light poles. Underground electrical conduit was installed in Area AC.
  • Vrabel Plumbing: Installed plumbing connections and underground drainage piping in Area AC.
  • First American (Mechanical): Installed piping beneath the existing IHS and began demolition and preparation for the new layout of the existing boiler room.

Schedule

  • Substantial completion for classroom addition: 7/14/2028
  • Substantial completion for Performing Arts Center addition: 7/12/2030

View the complete monthly progress update

Aerial view of construction site between two high schools
Aerial view of construction site between two high schools with a view of exterior structuring
Aerial view of construction site near a parking lot of a high school