July 17, 2026

General Contractor

  • Continued construction of the building’s foundation, including footers, stem walls and column supports.
  • Continued building exterior walls below ground level and began masonry work for the first emergency exit stairwell and elevator shaft.
  • Began excavation for the new parking area near the Senior High School entrance.
  • Steel delivery is scheduled for Aug. 3.

Electrical Contractor

  • Continued installing underground electrical infrastructure for the building’s main electrical room.
  • Began installing the new main electrical power loop around the west side of campus.

Plumbing Contractor

  • Continued installation of new underground sanitary sewer and stormwater piping.
  • Rerouted existing water, sanitary sewer and stormwater lines to accommodate the construction.

Mechanical Contractor

  • Continued removing existing piping in the boiler room and crawl space to prepare for new systems.
  • Began initial installation of new piping and equipment in the boiler room.
Construction process on secondary campus