Project Updates

June 18, 2026

June 2026 project update aerial

The classroom addition (Phase 1) has reached another important milestone. Site demolition has been completed, and installation of footers, stem walls and column pads began in May and remains underway. 

 

June 2026 aerial view of construction site
SV Aerial image of secondary campus construction